On October 14, 2014, Posted by , In Fibre Optics, Projects 

Perform Pre-Engineering work, Fibre Optic installation, testing & hand-over for 2km of underground &
10km of Aerial construction.

The client Broadband Infraco employed Optipower to provide a 10km Fibre Optic Cable connection from
Albany Substation to Rhodes University.  This included the installation of wood pole structures, trenching,
installation of underground cable ducting, splicing and testing and various road and bridge crossings.